Durban’s equipment fix runs to 2028
The minister says February, but the plan says 2028
Durban Gateway Terminal (DGT) has set out when its new equipment will arrive. The last of it is due in March 2028. The National reported the timeline on 21 November. 16 new rubber-tyred gantry cranes will be delivered in two batches, in December 2027 and March 2028. RTGs are the wheeled cranes that stack and unstack containers in the yard.
The same plan says 26 second-hand straddle carriers arrive by the end of the first quarter of 2027, and 12 new ones by the third quarter. Straddle carriers are the tall, four-legged machines that carry boxes between the ship-to-shore cranes and the stacks. When there aren’t enough working straddle carriers, the quay cranes sit idle and ships wait.
Get The Freight Brief by email
What's going on in freight, in your inbox every morning. Free.
Our view is simple. This is not a backlog that clears by the end of summer. It is a terminal being rebuilt while it runs. Forwarders and shippers moving cargo through Durban should plan as if delays continue well into 2027, and treat any good week as a bonus rather than a trend.
What DGT has promised, and when
DGT is Durban’s main container terminal. Transnet holds 51%, The National reported. The Philippine operator ICTSI has run it since January under a 25-year partnership, EWN reported. Kuehne+Nagel reported in May that the Pier 2 site “accounts for almost three-quarters of the port’s throughput.” When DGT slows, Durban slows.
DGT’s statement, reported by The National, blames years of underinvestment and poor maintenance for unsafe equipment. It acknowledged “the continued service shortcomings and the unfortunate impact on our clients and partners.” It said: “All efforts are being undertaken to clear the vessel backlog as soon as possible.”
The timeline, word for word from the report:
- “Sixteen new reach stackers and empty-container handlers are expected by the end of November 2026.”
- “Twenty-six second-hand straddle carriers are expected in two batches by the end of the first quarter of 2027.”
- “Twelve new straddle carriers are expected by the third quarter of 2027.”
- “Sixteen new rubber-tyred gantry cranes will be delivered in two batches in December 2027 and March 2028.”
DGT is also refurbishing existing cranes and straddle carriers and installing generators and backup power against unstable electricity supply. It says its new terminal operating system, NAVIS N4, is running well, and it has added a truck appointment system. DGT gives the current dwell time for full import containers as three days. Dwell time is how long a box sits in the terminal between discharge and release.
The first batch matters least. Reach stackers and empty handlers are useful, but they mostly shift empties and work the yard edges. They do not speed up the quay. The machines that do are due by the end of March 2027, and many of those are second-hand.
The queue the plan has to clear
The three-day dwell figure describes boxes already landed. It says nothing about the wait to land them. That wait is the problem.
Maritime consultant Dave Watts told Daily Maverick on 11 November: “The vessel that arrives today at anchorage won’t receive any kind of service for 12 days.” He added: “Add on the four days to service.” Then “it takes a couple of days to get them out, if we’re lucky,” because “the congestion on the land side is also quite drastic.” Anchorage is where ships wait offshore for a berth.
Peter Besnard of the South African Association of Ship Operators and Agents told the same paper: “This morning, there were 42 vessels at anchorage.”
Jacob van Rensburg of the South African Association of Freight Forwarders (SAAFF) said current conditions were “adding around 20 days to affected supply chains.” He also said: “DGT has stabilised, but not recovered – the stronger weekly throughput has not yet produced sustained backlog reduction.”
EWN reported on 16 November that SAAFF’s latest Cargo Movement Update showed “waterside volumes down 19%, with 13 to 14 vessels still at anchorage.” The National’s 21 November report mentions businesses facing delays of up to 20 days before transhipment. Transhipment is when a box is moved from one ship to another at an intermediate port.
Compare that with August. Kuehne+Nagel reported on 11 August that vessels calling at DGT were “experiencing average anchorage times of 80 hours during the month.” That is just over three days. On Watts’s figure, the wait is now more than three times as long.
Even urgent cargo is moving slowly. Transnet said the Department of Health had flagged pharmaceutical products on 16 vessels. Six vessels have been completed and their containers have left the port, Transnet said. Three were due to berth, one at Pier 1 and two at DGT. “Seven vessels were still approaching South African ports and had not yet nominated where they would berth.” A plan to discharge urgent containers at other terminals was still being considered. If a government priority list is less than half done, ordinary cargo should expect to wait.
Why the minister’s window looks too short
Transport Minister Barbara Creecy “expects DGT to recover between December and February as new equipment arrives,” EWN reported. In the same sentence, it said “Kuehne+Nagel does not expect meaningful improvement before the end of the first quarter of 2027.”
Put those beside DGT’s own dates. Between December and February, the only new equipment due is the reach stackers and empty handlers, which should already be on site. The second-hand straddle carriers are only promised by the end of March, after that window closes. The new straddle carriers are due by the third quarter. The new yard cranes come in December 2027 and March 2028.
So on DGT’s own schedule, Kuehne+Nagel’s view looks closer to the truth than the minister’s. Our reading: a summer recovery would need the refurbished fleet to perform much better than it has, at the same time as the post-holiday import rush.
There is a productivity promise to watch too. Daily Maverick columnist Stephen Grootes wrote on 17 November that when the ICTSI deal was signed, about a year ago, crane moves per hour were expected to rise “from 18 to 28.” Kuehne+Nagel had described 18 moves an hour as slow back in May. Our view: until the straddle carrier fleet is rebuilt, the quay cranes cannot get anywhere near 28, because boxes have nowhere to go.
Dr Simphiwe Madikizela of Unisa welcomed the plan but was cautious. “However, I would be cautious about concluding that these measures will be sufficient to resolve the crisis,” he told The National. “The fundamental challenge at DGT is a combination of operational inefficiencies, equipment constraints” and other factors, he said. He added that some interventions “may provide temporary relief without necessarily resolving” the structural weaknesses.
Watts himself put recovery further out. He said new DGT equipment would arrive “probably in the middle of next year,” and that “in a year, maybe 18 months, we will look back on this and say, ‘Geez, what a disaster.’”
What forwarders should do now
The costs are already showing up in company results. EWN reported that auto-components group Metair “has already flagged a 20% to 25% year-on-year fall in Ebitda, partly because of congestion costs.” Ebitda is earnings before interest, tax, depreciation and amortisation. Our reading: manufacturers that rely on imported parts through Durban are running on thinner buffers than they planned for.
Here is what we think this means in practice:
- Quote longer. Add two to three weeks to Durban transit estimates for import and export boxes. SAAFF’s 20-day figure is the best published guide. Tell customers in writing that this is a port delay, not a carrier one.
- Ask about other berths. DGT is offering shipping lines alternative berths at DCT Pier 1, Maydon Wharf berth 102 and Ngqura Container Terminal near Gqeberha. Ngqura means a longer road or rail leg to Gauteng, but it may beat a 12-day anchorage. Ask carriers which services are actually diverting, not just which are allowed to.
- Lock down charges. Long anchorage waits eat into free time once boxes land. Agree detention and demurrage terms before the cargo sails. Detention is the charge for keeping a carrier’s container too long outside the terminal. Demurrage is the charge for leaving it inside.
- Book ahead of Chinese New Year. Exporters in Asia will rush cargo out before the holiday. That wave will reach Durban in February and March, before all the second-hand straddle carriers are due. Shippers with spring production schedules should move cargo earlier, or split it across ports.
- Watch the transhipment hubs. Cargo for Mauritius and the Indian Ocean islands already gets rerouted when Durban backs up. In August, Maersk and CMA CGM dropped the next two eastbound Port Louis calls from their Safari service and rerouted that cargo via Tanjung Pelepas, Kuehne+Nagel reported. Expect more of these changes.
Our call
Our call: Durban’s port-wide planning indicator in the BUSA Cargo Movement Update will still be 10 days or more in the last update of January 2027. The pre-Chinese New Year surge will arrive before the backlog clears. DGT’s own timeline supports this, because the second-hand straddle carriers are not due in full until the end of March.
We also expect at least one more listed South African manufacturer, beyond Metair, to flag Durban delays as a material earnings risk before the end of Q1 2027.
Sources