Barking derailment keeps London Gateway on trucks into mid-November

Barking repairs run to at least 10 November. London Gateway shippers should plan for three weeks on the road

National Rail now expects disruption on the railway near Barking “until at least the end of the day on Tuesday 10 November.” Its notice was last updated in the early hours of Sunday 1 November. The cause is a freight train that partially derailed between Woodgrange Park and Barking at lunchtime on Friday 23 October. That train had just left London Gateway.

If the 10 November date holds, the line will have been disrupted for 18 days. It may not hold.

Our view is simple. This is not the one-week blip that the first carrier advisory suggested. It is a three-week inland problem for London Gateway at least, and the cost is landing on forwarders and their hauliers rather than on the shipping lines. Anyone with import boxes landing at London Gateway in the next fortnight should plan as if rail is unavailable.

What happened on 23 October

RaillyNews reported on 26 October that “At about 13:10 on 23 October the freight train that had departed London Gateway left the rails near Barking.” It named the operator as GB Railfreight. It said no one was hurt and no passengers were on board.

The damage is extensive. According to RaillyNews, “The derailment directly damaged the track alignment and some sleepers across a corridor roughly 1.2 kilometers long.” Sleepers are the beams that hold the rails in place. RaillyNews also reported that platforms 7 and 8 at Barking were taken out of use, and that the operators were coordinating with the Rail Accident Investigation Branch (RAIB), the UK’s independent rail accident investigator.

The National Rail notice confirms the scale in plainer words: “Some lines remain closed as significant damage has been caused to the railway infrastructure.” It says there are no c2c passenger trains between Barking and Grays via Dagenham Dock, Rainham and Purfleet. London Overground’s Suffragette line is suspended between South Tottenham and Barking Riverside, with a reduced service between Gospel Oak and South Tottenham.

The date keeps moving. RaillyNews reported on 26 October that operators were warning of disruption until at least 29 October. By 1 November, National Rail’s notice said 10 November. RaillyNews said the reopening date depends on how long it takes to remove the wagons, repair ballast and sleepers, and fix any signalling or earthworks problems found once engineers dig in. Those are the kind of jobs that tend to grow, not shrink, once work starts.

One caveat matters. The National Rail notice is written for passengers. It does not say when freight paths to London Gateway will reopen. Freight could come back slightly earlier or later than passenger trains. Nobody has published a freight-specific date.

What Hapag-Lloyd told customers

Container News reported Hapag-Lloyd’s advisory on 30 October. The carrier said rail services to and from London Gateway were suspended. In Container News’s words, “Based on the latest information available to the carrier, the disruption is expected to continue for at least one week.”

The detail is in how it splits customers.

Merchant haulage customers arrange their own inland transport. Ramp customers collect from a rail terminal. Both groups were told to have their own transport providers collect the cargo by truck.

Carrier haulage customers are those who pay the shipping line to deliver the box inland. Existing bookings will be handled by Hapag-Lloyd’s inland team, which will contact customers about alternatives. New bookings are a different story. Container News reports that “The carrier will not accept additional Carrier Haulage requests during the disruption.” The report adds that this applies even when customers cannot get trucks through their own providers.

Read that last point twice. The carrier is not just warning of delay. It is stepping back from the inland leg and handing the problem to the customer’s own haulier.

Hapag-Lloyd’s “at least one week” from 30 October points to about 6 November. National Rail’s latest date is four days later. The carrier’s estimate was made before the latest update, so it is already behind.

What happened last time

There are two useful precedents.

The closest is at the port itself. On 24 December 2021, five wagons of a 33-wagon train derailed at low speed as it entered the London Gateway rail terminal. RAIB’s report, published on 19 December 2023, says: “While no one was injured, infrastructure damage disrupted rail freight access into and out of the port for 14 days.” That was a slow, low-speed derailment inside the terminal. It still took two weeks.

The second is on the Gospel Oak to Barking line in early 2020. A freight wagon derailed on 23 January 2020. On the day, Network Rail said its “initial assessment is that repairs will take several days”, adding that further examination was required. By 14 February, three weeks later, the line was still part-suspended. Network Rail said “the date for reopening the line will be confirmed next week.” It had found that “More than two and a half miles of the route between Barking and South Tottenham was damaged.” The repair needed 39 pieces of rail, 5,300 concrete sleepers, 900 wooden sleepers and 10,000 tonnes of ballast, Network Rail said.

That 2020 damage covered a longer stretch than the roughly 1.2 km reported this time. But the pattern is the point. The first estimates were too short in 2020, and they have been too short again this time. “Several days” became more than three weeks. Repair dates slip when engineers find more damage once they start work.

What it means for forwarders

The cost is moving down the chain. Here is how it lands.

Trucks. Import boxes heading for the Midlands and the North usually travel by rail from London Gateway to inland terminals. With rail out, they need a truck for the full distance. That ties up a haulier and a driver for a much longer round trip than a short local delivery. Expect hauliers to quote higher rates and to ration slots for London Gateway work.

Port charges. Every day a box sits at the terminal waiting for a truck can build up demurrage, which is the charge for leaving a full container at the port beyond the free time. Detention is the separate charge for keeping the carrier’s container beyond the agreed time outside the port. Neither stops just because the railway is broken. Ask your carrier in writing whether it will extend free time. Keep the evidence of the rail suspension on file. If it refuses, you will at least have a paper trail for a dispute later.

Booking choices. For cargo not yet on the water, look again at the discharge port. If your carrier’s service also calls at Felixstowe or Southampton, a switch may avoid the problem. Check the cost and timing of changing the discharge port before you commit. Both ports will be absorbing some of the same overflow.

Customer promises. If you sold a door-to-door rate that assumed rail from London Gateway, the margin on that job has probably gone. Tell the customer now. Agree in writing who pays the extra trucking before the box lands, not after.

Exports. Container News reports that Hapag-Lloyd’s suspension covers rail both to and from London Gateway, so the problem runs both ways. Export boxes that would normally travel to the port by train from an inland terminal now need a truck too. That matters for cut-off times, the deadline by which a box must reach the terminal to make its sailing. A box that misses cut-off waits for the next vessel, which can mean another week. Build in extra time for road delivery, and check whether your haulier can actually get a slot at the port before you promise a sailing.

Carrier haulage. If you rely on the line to book the inland leg, Hapag-Lloyd will not take new requests on this route while the disruption lasts. Have a backup haulier lined up. Other carriers serving London Gateway face the same broken railway, so their customers should check for advisories too.

Our call

Our prediction is in three parts.

First, Hapag-Lloyd will extend its London Gateway rail suspension beyond 6 November, in line with National Rail’s 10 November date.

Second, normal rail service to and from London Gateway will not resume before Friday 13 November. That is three weeks after the derailment. The 2021 terminal derailment took 14 days to clear. This one damaged a working main line and its expected end date has already slipped from 29 October to 10 November, so we expect it to take longer.

Third, Hapag-Lloyd will not reopen new carrier haulage bookings on London Gateway rail before the week starting 16 November. Lines tend to hold that kind of restriction until trains are running reliably, not just running.

If National Rail’s notice moves past 10 November, expect each of those dates to move with it. Book trucks now and assume rail is gone until mid-November.