Ocean Nov 17, 2026 · 7 min read

DP World pulls forward UAE terminals outside Hormuz

Tracker Red Sea and Hormuz: are ships going through? · 5.1 ships/day

The Gulf’s back door gets a date, and it is still 2028

DP World said on 16 November that its two new terminals near Fujairah could be operational in as little as 18 months. The Maritime Standard reported that this compares with “the minimum lead time of 24 months announced previously”. The sites are Al Rugaylat, a container and multi-purpose terminal, and Dibba, a general cargo terminal. Both are on the UAE’s east coast, on the Gulf of Oman, outside the Strait of Hormuz.

In our view, the faster timeline matters less than the commitment behind it. DP World is now building for a Gulf that has a permanent second gateway outside the strait. Forwarders should plan that way too. They should also be honest with customers about the gap. Even on the fastest schedule, the new berths arrive around May 2028. Until then, Gulf cargo keeps running on trucks.

What DP World announced

The timeline has tightened twice in four months.

In July, DP World signed an in-principle deal with the Fujairah Ports Authority for a 50-year concession. EnterpriseAM reported on 23 July that construction would be phased and was expected to take “24-30 months from the start of works”. No start date was given.

On 10 November, DP World’s GCC chief executive, Ahmad Yousef Al-Hassan, told Khaleej Times that both terminals were expected to be working within 18–24 months.

On 16 November, the company said “as little as 18 months”. The Maritime Standard reported the terminals will “proceed irrespective of whether the Strait is fully opened”.

The planned sizes have not changed. Al Rugaylat is designed for up to 2.5m TEU a year. (A TEU, or twenty-foot equivalent unit, is one standard small container.) It will also take 1.7m tonnes of general cargo and 190,000 CEU. (A CEU, or car equivalent unit, is the space one standard car takes on a car carrier.) Dibba is planned for up to 3.6m tonnes of general cargo a year.

DP World gave no investment figure. Nor did it say when the 18-month clock starts.

Why we think this is permanent

Three things point the same way.

First, DP World ties the build to no outcome in the strait. That is the plainest signal a port operator can give. It means the company expects shipping lines and cargo owners to want a route that does not depend on Hormuz, even in peacetime.

Second, the concession runs for 50 years. Nobody signs that for a crisis workaround.

Third, the company is moving faster, not slower, as the year goes on. A temporary fix would be quietly shelved once the worst passed. This one is being pulled forward.

But it is a second door, not a new house. Al-Hassan told Khaleej Times: “Fujairah is never a replacement or a backup only for Jebel Ali”. He also said it would take another 40–50 years to build a port with Jebel Ali’s scale, the paper reported. The numbers back him. Jebel Ali can handle 19.4m TEU a year, Khaleej Times reported. Al Rugaylat’s 2.5m TEU is about 13% of that. EnterpriseAM put DP World’s combined UAE container capacity at nearly 22m TEU once Fujairah is added.

DP World also expects most traffic to go back to Jebel Ali when it can. The Maritime Standard reports the company believes shipping lines want direct calls restored “as soon as possible”, and that services and volumes could recover within three months of safe passage being restored. A direct call means the ship sails straight into the port, with no transfer to trucks or another vessel.

So the likely shape is this. Jebel Ali stays the hub. Fujairah becomes a standing alternative that is always open, rather than an emergency route that has to be built each time.

What the land bridge looks like today

Today’s alternative is a land bridge: ships discharge on the east coast, and boxes go by road or rail to Jebel Ali or straight to customers.

It is running at real scale. From early March to the end of October, DP World moved more than 1m TEU this way, according to The Maritime Standard. It uses about 3,000 trucks. The same corridors also serve Sohar and Duqm in Oman and Jeddah in Saudi Arabia.

That is roughly 125,000 TEU a month on average (our arithmetic: 1m TEU over eight months). For scale, Jebel Ali handled 3.8m TEU in the second quarter of 2025, or roughly 1.27m TEU a month, according to Seatrade Maritime News. The land bridge moves a meaningful volume. It does not move a normal Jebel Ali volume.

Jebel Ali itself has stayed open. Al-Hassan told Khaleej Times: “We closed only six hours since the start of the war.” But ships have struggled to reach it. In the second quarter of 2026 the port handled 374,000 TEU, down 90.1% year on year, Seatrade Maritime News reported from DP World’s half-year results.

The cost is high. An unnamed company official told Semafor in August that alternative ports such as Fujairah and Khor Fakkan “can cost four to five times more once inland transport is included”. Semafor also reported “trucks facing queues of as long as 12 hours to enter and leave the alternative ports”, against a turnaround of about 27 minutes at Jebel Ali.

The hit shows in DP World’s own results. Semafor reported that group revenue rose 13% to $12.7bn in the first half, helped by more than 60 ports elsewhere. But “net profit for the first half was down 39% year-on-year.”

What it means for forwarders

Our reading for anyone moving cargo into or out of the Gulf:

Price the land bridge into 2028. The new berths will not be there to absorb east-coast cargo for at least 18 months. Until then, east-coast discharge means trucks, queues and inland haulage. Build those costs and transit buffers into quotes and contracts that run through 2027. Do not assume they fall away early.

Ask carriers where they will discharge. If Hormuz reopens, DP World expects lines to return to Jebel Ali within about three months. If it does not, east-coast ports carry the load. Contracts should say what happens to cargo, costs and free time in either case.

Watch Jafza customers. Jebel Ali Free Zone has close to 12,000 companies, Khaleej Times reported. Many of them rely on the port. A permanent east-coast option gives them a second route. It also means their supply chains may split between two gateways, with different dwell times and trucking costs.

Car and project cargo should look early. Al Rugaylat’s 190,000 CEU and Dibba’s 3.6m tonnes of general cargo mean the east coast will handle more than containers. Forwarders moving vehicles, machinery and breakbulk into the UAE should track the build closely. These cargoes are the hardest to shift by truck today.

Do not over-plan around the timeline. “As little as 18 months” is a best case. No report gives a start date for the clock or a published budget. Ports rarely open on their fastest schedule. Treat mid-2028 as the earliest date, not the planning date.

What happened before, and what we expect

In March, when the strait first shut, DP World had to work with what already existed. MEED reported on 13 March that group chief executive Yuvraj Narayan put Khorfakkan’s capacity at about 5m TEU and Fujairah’s at under 1m TEU. He indicated that was not enough to replace lost volume at Jebel Ali, which handled 15.6m TEU in 2025. He also pointed to Red Sea ports such as Jeddah and Sokhna picking up traffic.

That is the gap the new terminals are meant to narrow. Eight months on, the network has bent around the blockage, through the land bridge and through other ports. What is different now is that DP World is pouring concrete for it. The March response relied on existing ports and spare capacity. This one adds new, purpose-built capacity outside the chokepoint, on a 50-year lease.

Our prediction: no commercial vessel will call at Al Rugaylat before the second half of 2028. Eighteen months from 16 November is mid-May 2028. Port projects seldom beat their best-case dates, and no start of works has been made public. We expect the first call between July and December 2028. Until then, the east-coast land bridge stays the Gulf’s main bypass for cargo, at about the scale it runs today.

Sources